VOLT method · the pilot in 30 days
We design backwards.
Most projects start by installing sensors. We start with the decision you have to make — and we only measure what serves that decision.
In 30 days, one line measured on site, its downtime costed in euros and the cost of each option calculated for your critical assets. No changes to your PLCs, no production stoppage, no vendor lock-in.
Visit & scope
We start from the decision: your options, their costs and your intervention lead time, for 3 to 5 critical assets. Success criteria written and signed.
Open the data
A box on site, read-only collection (Modbus, OPC-UA, MQTT). Nothing is changed in your PLCs.
Log & cost
Downtime, OEE and energy on screen, alerts, and the cost of each option for your critical assets.
Train & hand over
Hardening, documentation, training for two people, costed review on day 30.
Then edgeSentinel runs continuously: see, understand, decide, act.
Decision engine
Expected cost = probability × cost of failure + cost of the action
To plan, the probability is reduced to the residual risk before the intervention date.
- WaitRecommended0.77 × €20,000 + €0€15,400
- PlanRecommended0.15 × 0.77 × €20,000 + €2,50015%: residual risk before the planned date€4,810
- Act nowRecommendedimmediate stop · €5,200€5,200
Fictitious amounts: replace them with your own.
wait → plan from 14.7% · act now from 90%The operator decides.
Want to cost your own figures with your team? The diagnostic starts from your numbers, not ours.